July 11, maybe start the grinding and paving , maybe 5 days a week , maybe 7AM-7PM ,may start on the town section maybe start up in the Portal. Kinda behind right now but when they start it will be a ride,
This puts the major paving during the peak season so with the normal traffic, paving machines, rollers and endless line of dump trucks moving at crawl speed up the mountain and cars overheating and a few brakes/ transmissions overheating plan for longer delays. Start early if you can, reach the Portal before 7 AM .
A major concern is the constant grade up the road , trucks will overheat if overloaded and the asphalt plant is in Ridgecrest.The turn around time for each truck will be 3 hours, and as always most road jobs are done during the summer so if they have not contracted for haul trucks and all the machines needed that could be a problem also.
Good news the switchbacks will be open and time for the annual 2 weeks of rain and flooding! Jack and Betsy will be arriving so as the story goes.......